PMP Practice Question: Process — Predictive, Hard

Your construction project has a 16-month duration with four major phase gates requiring customer sign-off. You are currently in month 11, approaching the third phase gate. Quality inspections reveal that 23% of the concrete structural work completed in the previous phase has microfractures that don't meet specifications, likely due to temperature control issues during curing. The work passed initial inspections but was caught during detailed pre-gate review. Remediation will cost $1.2M and delay the phase gate by 8 weeks. The customer relationship is already strained from previous minor delays. The quality manager suggests accepting the work since the microfractures are within building code minimums, though not project specifications. What is the BEST course of action?