PMP Practice Question: People — Predictive, Medium
You are three months into a 12-month predictive project when your most experienced business analyst announces she will be leaving the company in four weeks. She is the only team member who fully understands the complex regulatory requirements that drive 40% of project deliverables. The project baseline schedule shows her involvement is critical for the next six months. What is your best course of action?
Study this topic
- 📖AI in Project Management: Your 2026 PMP Exam Guide
Master AI concepts for the 2026 PMP exam. Learn how artificial intelligence impacts project management, what you need to know for test day, and practical applications.
- 📖Resource Management Techniques: Building High-Performing Teams
Master resource management techniques for the PMP exam—from team development to capacity planning. Learn how to optimize human, material, and financial resources for project success.
- 🗂️Flashcards: Leadership, Team & Stakeholder Models
15 cards · quick recall practice
More People Questions
View all →You are leading a manufacturing facility construction project following a predictive lifecycle. The project team consists of 15 members, including contractors and internal staff. After three months of work, you receive feedback from several team members that the weekly status meetings are too long and not productive. Team members feel they spend too much time listening to updates irrelevant to their work. The meetings currently last 90 minutes and cover all work packages. What is the best approach to address this concern?
A cross-functional agile team is preparing for their next sprint. During sprint planning, the QA specialist expresses concern that the team has been committing to user stories without adequately considering testing effort. She feels that her input is often sought too late in the process, after developers have already estimated and committed to stories. This has resulted in quality issues and testing becoming a bottleneck in the last two sprints. The team wants to improve but is unsure how to better integrate QA perspective earlier. What should the team do?
Your organization is piloting agile practices within traditionally predictive portfolios. You're leading a hybrid project with a co-located agile team and distributed predictive workstreams across three continents. After four months, you notice the agile team has strong cohesion and high performance, but the distributed predictive teams report feeling disconnected and undervalued. Several key resources from the predictive workstreams have requested transfers, citing lack of engagement. Executive stakeholders are questioning whether the hybrid approach is sustainable. What is the MOST effective way to address this disparity?