ProcessHybridMediumECO: Process Task 5.2

Your organization is implementing a new enterprise software system using a hybrid approach. The infrastructure setup and data migration follow a predictive waterfall model, while feature configuration and user acceptance testing use iterative cycles. You've just completed the second iteration of user testing when stakeholders request a major change to the data migration strategy that would affect already-configured features. The change would improve data quality but requires re-work of completed iterations. How should you handle this request?