ProcessAgileMediumECO: Process Task 3.2

Your Kanban team is experiencing flow problems on a data migration project. The team's board shows 15 items in the 'In Progress' column, 8 items in 'Code Review', and only 3 items in 'Done' over the past two weeks. Team members report feeling overwhelmed and context-switching frequently between multiple work items. Lead time for items has increased from an average of 5 days to 12 days. The team lead suggests adding more people to help clear the backlog. What is the most appropriate action to improve flow?