You are managing a hybrid project where the development team works in two-week sprints while the infrastructure team follows a waterfall approach with phase gates. During sprint planning, the development team commits to features that require infrastructure changes, but the infrastructure team is still in the design phase and cannot commit to delivery dates. This misalignment has caused three consecutive sprints to end with incomplete work. Team morale is declining, and stakeholders are questioning the project's viability. What should you do first to address this systemic issue?