PMP Practice Question: Process — Hybrid, Easy
Your hybrid project includes a hardware component managed predictively and a software component managed using Kanban. The hardware team reports they are on schedule, but the software team's Kanban board shows several items stuck in the 'In Progress' column for over two weeks. The team's work-in-progress (WIP) limit is being exceeded. As the project manager, what should you do?
Study this topic
- 📖Kanban for Project Managers: What You Need to Know
Master Kanban principles, WIP limits, and flow optimization for the PMP exam. Learn how this Agile framework supports continuous delivery and project success.
- 📖PMI-ACP After PMP: Your 2026 Certification Pathway
Already have your PMP? Learn how to leverage your certification toward PMI-ACP, including prerequisites, exam structure, and strategic preparation advice for 2026.
- 🗂️Flashcards: Agile, Scrum & Hybrid Concepts
15 cards · quick recall practice
More Process Questions
View all →You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. During month 6, you conduct an earned value analysis and discover that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks you to forecast the final project cost and determine what actions are needed. Using the current performance trends, what is the most appropriate estimate at completion (EAC) if you believe current variances are atypical and future work will be performed at the planned rate?
You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?
You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?