During sprint planning, your development team commits to 25 story points based on their historical velocity. However, the product owner insists that 35 story points must be completed this sprint to meet a critical market window. The product owner escalates to senior management, who pressure you to have the team commit to the higher number. The team is frustrated and feels their professional judgment is being dismissed. What is the best way to handle this situation?