PMP Practice Question: Process — Hybrid, Easy
You are managing a hybrid project where the design phase follows a predictive approach and the development phase uses iterative sprints. The design team has completed their work and handed off specifications to the development team. However, the development team reports that several requirements are unclear and need clarification. The design team has already moved on to another project. What should you do first?
Study this topic
- 📖Managing Virtual and Remote Project Teams: A PMP Perspective
Learn proven strategies for leading distributed teams effectively, from communication protocols to trust-building, aligned with PMBOK 8th Edition principles.
- 📖Stakeholder Engagement Strategies for Project Success
Master proven stakeholder engagement techniques for the PMP exam and real-world projects. Learn assessment frameworks, communication tactics, and conflict resolution strategies aligned with PMBOK 8.
- 🗂️Flashcards: Leadership, Team & Stakeholder Models
15 cards · quick recall practice
More Process Questions
View all →You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. During month 6, you conduct an earned value analysis and discover that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks you to forecast the final project cost and determine what actions are needed. Using the current performance trends, what is the most appropriate estimate at completion (EAC) if you believe current variances are atypical and future work will be performed at the planned rate?
You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?
You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?