PMP Practice Question: Process — Agile, Easy
You are managing an agile software development project. The product owner has created a product backlog with 50 user stories but hasn't prioritized them yet. The development team is ready to start their first sprint planning meeting tomorrow. The product owner asks you what preparation is needed before the sprint planning session. What is the most important thing the product owner should do?
Study this topic
- 📖Earned Value Management: Complete PMP Exam Study Guide
Master EVM formulas, interpretation, and application for the PMP exam. Learn how earned value management integrates with agile, hybrid, and predictive approaches in the 2026 ECO.
- 📖AI in Project Management: Your 2026 PMP Exam Guide
Master AI concepts for the 2026 PMP exam. Learn how artificial intelligence impacts project management, what you need to know for test day, and practical applications.
- 🗂️Flashcards: Agile, Scrum & Hybrid Concepts
15 cards · quick recall practice
More Process Questions
View all →You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. During month 6, you conduct an earned value analysis and discover that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks you to forecast the final project cost and determine what actions are needed. Using the current performance trends, what is the most appropriate estimate at completion (EAC) if you believe current variances are atypical and future work will be performed at the planned rate?
You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?
You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?