ProcessHybridMediumECO: Process Task 2.7

PMP Practice Question: Process — Hybrid, Medium

You are leading a product development project using a hybrid approach where research and regulatory approval follow a waterfall process, while feature development uses Kanban. The regulatory team has just received approval for the product specifications, which is a major milestone. However, during the regulatory review process, the development team continued building features based on the submitted specifications and has now completed 60% of the planned features. The approved specifications include three changes from what was originally submitted. What should you do next?