PMP Guide — Empowering Project Managers
ProcessHybridMediumECO: Process Task 2.7

PMP Practice Question: Process — Hybrid, Medium

Your organization is transitioning to hybrid project management. You are managing a project where requirements gathering and architecture design follow a plan-driven approach, while development and testing use Scrum with two-week sprints. After three sprints, the cumulative flow diagram shows that completed story points are consistently 20% below the planned velocity, while the predictive architecture work is on schedule. Stakeholders are concerned about meeting the final delivery date. What should be your primary focus?

← All questions

Study this topic

PMP Practice Question — Process · Medium | PMP Guide