You are leading a product development project using a hybrid approach where regulatory compliance work follows a predictive model and feature development follows an agile model. During a retrospective, the agile team expresses frustration that they completed several features in the last sprint, but these features cannot be released to customers until compliance documentation is approved, which takes four weeks. The team feels their work is not creating value quickly enough. What is the best way to address this concern?