PMP Practice Question: Process — Agile, Hard

Your agile project has been using relative estimation with story points for six months. A new senior stakeholder joins and demands to know exactly when specific features will be delivered, expressing frustration with 'vague agile estimates.' They insist the team provide hour-based estimates and commit to fixed delivery dates for features, stating that their previous projects always worked this way successfully. The team's velocity has been stable at 30-35 points per sprint, and they have a well-groomed backlog. The stakeholder threatens to escalate to executive leadership if you cannot provide 'real project management.' How should you respond?