PMP Practice Question: Process — Agile, Hard
Your agile project has been using relative estimation with story points for six months. A new senior stakeholder joins and demands to know exactly when specific features will be delivered, expressing frustration with 'vague agile estimates.' They insist the team provide hour-based estimates and commit to fixed delivery dates for features, stating that their previous projects always worked this way successfully. The team's velocity has been stable at 30-35 points per sprint, and they have a well-groomed backlog. The stakeholder threatens to escalate to executive leadership if you cannot provide 'real project management.' How should you respond?
Study this topic
- 📖Emotional Intelligence for the PMP Exam 2026: Master the People Domain
Emotional intelligence accounts for crucial skills tested across the People domain (33%) in the 2026 PMP exam. Learn how EI appears in scenarios, key competencies, and proven study strategies.
- 📖Servant Leadership in Agile Project Management (2026 PMP)
Master servant leadership for the 2026 PMP exam. Learn how this critical agile approach drives team performance, aligns with PMBOK 8, and supports the People domain.
- 🗂️Flashcards: Leadership, Team & Stakeholder Models
15 cards · quick recall practice
More Process Questions
View all →You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. During month 6, you conduct an earned value analysis and discover that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks you to forecast the final project cost and determine what actions are needed. Using the current performance trends, what is the most appropriate estimate at completion (EAC) if you believe current variances are atypical and future work will be performed at the planned rate?
You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?
You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?