PMP Practice Question: Process — Hybrid, Easy
A project manager is leading a hybrid project where the design phase was completed using a predictive approach, and now the team is moving into iterative development sprints. Several team members who were not involved in the design phase are confused about the project requirements. Velocity has been lower than expected in the first sprint. What should the project manager do?
Study this topic
- 📖Building High-Performing Teams: PMBOK 8 Principles
Master the PMBOK 8 approach to creating collaborative, empowered teams. Learn practical strategies for team development, conflict resolution, and performance optimization.
- 📖Resource Management Techniques: Building High-Performing Teams
Master resource management techniques for the PMP exam—from team development to capacity planning. Learn how to optimize human, material, and financial resources for project success.
- 🗂️Flashcards: Leadership, Team & Stakeholder Models
15 cards · quick recall practice
More Process Questions
View all →You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. During month 6, you conduct an earned value analysis and discover that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks you to forecast the final project cost and determine what actions are needed. Using the current performance trends, what is the most appropriate estimate at completion (EAC) if you believe current variances are atypical and future work will be performed at the planned rate?
You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?
You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?