PMP Guide — Empowering Project Managers
ProcessPredictiveMediumECO: Process Task 4.2

PMP Practice Question: Process — Predictive, Medium

Your manufacturing project is in the execution phase with a CPI of 0.92 and an SPI of 1.05. During a quality audit, the quality assurance team discovers that several deliverables do not meet the specifications defined in the quality management plan. The project sponsor is pleased with the schedule performance and is pressuring you to maintain the current pace. Rework to fix the quality issues would cost an additional $40,000 and require 2 weeks. What should you do?

← All questions

Study this topic