PMP Practice Question: Process — Hybrid, Medium

A project manager is leading a hybrid project to develop a new mobile application with backend infrastructure upgrades. The infrastructure work uses a predictive approach with detailed plans and change control, while the application development follows Scrum practices. Three months into the project, the cumulative flow diagram shows that work items in the 'testing' state have been increasing steadily, while the 'done' column shows minimal progress. The predictive infrastructure tasks are on schedule. What should the project manager do to address this situation?