PMP Practice Question: ProcessAgile, Hard

During the eighth sprint of a financial services product, a regulatory compliance requirement emerges that affects the system's data retention architecture. The compliance officer estimates implementation requires 320 hours of effort, equivalent to four full sprints of the eight-person team's capacity. The product owner has a committed release date in six sprints to support a major client contract worth $2.3M annually. The current product backlog contains 180 story points of features promised for this release. The team's average velocity is 45 story points per sprint. How should the team approach this situation?