PMP Practice Question: People — Hybrid, Hard
You are managing a hybrid project where the development team uses Scrum while the compliance and regulatory workstreams follow a predictive approach. During sprint planning, a senior compliance officer insists on attending all Scrum ceremonies and has been providing detailed instructions to developers, effectively bypassing the Product Owner. Team velocity has dropped 30% over two sprints, and developers privately express frustration about conflicting priorities. The compliance officer believes their involvement is necessary due to regulatory risks. How should you address this situation?
Study this topic
- 📖Emotional Intelligence for the PMP Exam 2026: Master the People Domain
Emotional intelligence accounts for crucial skills tested across the People domain (33%) in the 2026 PMP exam. Learn how EI appears in scenarios, key competencies, and proven study strategies.
- 📖Conflict Resolution Techniques Every Project Manager Needs
Master the five core conflict resolution techniques tested on the PMP exam. Learn when to collaborate, compromise, or withdraw using real project scenarios.
- 🗂️Flashcards: Leadership, Team & Stakeholder Models
15 cards · quick recall practice
More People Questions
View all →You are managing a construction project using a predictive approach. The project is in the execution phase, and you have a baseline schedule with clearly defined milestones. One of your key team members, who is responsible for electrical installations, requests three weeks of leave for personal reasons during a critical phase of the project. This team member has specialized expertise that is difficult to replace. The leave would occur just before a major milestone delivery. What is the BEST course of action?
You are leading a manufacturing facility construction project following a predictive lifecycle. The project team consists of 15 members, including contractors and internal staff. After three months of work, you receive feedback from several team members that the weekly status meetings are too long and not productive. Team members feel they spend too much time listening to updates irrelevant to their work. The meetings currently last 90 minutes and cover all work packages. What is the best approach to address this concern?
You are leading a manufacturing implementation project using a predictive lifecycle. The project team consists of members from three different departments who have not worked together before. After one month of execution, you observe that team members primarily communicate within their departmental groups, and cross-functional collaboration is minimal. Work hand-offs between departments are experiencing delays and quality issues. The project charter emphasizes the importance of integrated teamwork for project success. What should you do to improve this situation?