PMP Guide — Empowering Project Managers
ProcessPredictiveMediumECO: Process Task 6.2

PMP Practice Question: ProcessPredictive, Medium

You are managing a construction project with a 12-month timeline and a fixed budget of $2.5 million. During the fourth month, you conduct an earned value analysis and find that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The sponsor asks you to forecast the final project cost assuming current performance continues. What is the most appropriate estimate to provide?

← All questions
📖

Study this topic

WBS Work Breakdown Structure: Proven Best Practices

Master the essential techniques for creating effective Work Breakdown Structures that drive project success and align wi

More Process Questions

View all →