PMP Practice Question: Process — Predictive, Medium

You are managing a construction project with a 12-month timeline and a fixed budget of $2.5 million. During the fourth month, you conduct an earned value analysis and find that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The sponsor asks you to forecast the final project cost assuming current performance continues. What is the most appropriate estimate to provide?