Your hybrid project uses iterative development for product features while marketing and compliance activities follow a predictive timeline. The compliance team has just informed you that a regulatory requirement will change in three months, affecting features currently in the product backlog. The change is mandatory but the detailed requirements won't be available for six weeks. How should you respond?