Your hybrid project uses iterative development for customer-facing features and predictive planning for regulatory compliance activities. During a retrospective, the development team reports that compliance reviews are causing significant delays because compliance work is scheduled in sequential phases without team input. The compliance manager insists on following the approved plan to ensure audit readiness. Team morale is declining as they feel the rigid compliance process contradicts the adaptive approach they use for features. How should you address this situation?