PMP Practice Question: People — Agile, Medium

Your agile team has two developers who consistently clash during daily standups and sprint planning. One developer prefers thoroughly discussing technical approaches before committing to work, while the other prefers to start coding quickly and iterate. Their disagreements are starting to affect team dynamics, with other team members avoiding engaging in technical discussions. Both developers are highly skilled and their work quality is excellent. Yesterday, their disagreement during refinement caused the session to run 30 minutes over time. What should you do?

← All questions
📖

Study this topic

PMI-ACP vs CSM vs SAFe: Which Agile Certification After PMP?

PMPs often pursue additional agile credentials. Compare PMI-ACP, CSM, and SAFe certifications to determine which best al…

More People Questions

View all →
1
MediumPredictive

You are leading a manufacturing facility construction project following a predictive lifecycle. The project team consists of 15 members, including contractors and internal staff. After three months of work, you receive feedback from several team members that the weekly status meetings are too long and not productive. Team members feel they spend too much time listening to updates irrelevant to their work. The meetings currently last 90 minutes and cover all work packages. What is the best approach to address this concern?

→
2
MediumAgile

A cross-functional agile team is preparing for their next sprint. During sprint planning, the QA specialist expresses concern that the team has been committing to user stories without adequately considering testing effort. She feels that her input is often sought too late in the process, after developers have already estimated and committed to stories. This has resulted in quality issues and testing becoming a bottleneck in the last two sprints. The team wants to improve but is unsure how to better integrate QA perspective earlier. What should the team do?

→
3
HardHybrid

Your organization is piloting agile practices within traditionally predictive portfolios. You're leading a hybrid project with a co-located agile team and distributed predictive workstreams across three continents. After four months, you notice the agile team has strong cohesion and high performance, but the distributed predictive teams report feeling disconnected and undervalued. Several key resources from the predictive workstreams have requested transfers, citing lack of engagement. Executive stakeholders are questioning whether the hybrid approach is sustainable. What is the MOST effective way to address this disparity?

→