PMP Practice Question: Process — Agile, Medium
You are managing an agile project for developing a customer relationship management (CRM) system. After four iterations, the team has consistently delivered all committed story points, but customer feedback indicates that the features delivered are not addressing their most critical pain points. The Product Owner has been creating user stories based on what they think customers need rather than direct customer input. Velocity is stable, but customer satisfaction is declining. What is the most appropriate action to take?
Study this topic
- 📖Business Case Development and Project Justification
Master business case development for PMP success. Learn how to justify projects, align with strategy, and demonstrate value delivery to stakeholders.
- 📖Stakeholder Engagement Strategies for Project Success
Master proven stakeholder engagement techniques for the PMP exam and real-world projects. Learn assessment frameworks, communication tactics, and conflict resolution strategies aligned with PMBOK 8.
- 🗂️Flashcards: Agile, Scrum & Hybrid Concepts
15 cards · quick recall practice
More Process Questions
View all →You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. During month 6, you conduct an earned value analysis and discover that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks you to forecast the final project cost and determine what actions are needed. Using the current performance trends, what is the most appropriate estimate at completion (EAC) if you believe current variances are atypical and future work will be performed at the planned rate?
You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?
You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?