PMP Guide — Empowering Project Managers
ProcessAgileHardECO: Process Task 2.13

PMP Practice Question: Process — Agile, Hard

You're managing a complex product with three agile teams working on interdependent features. During sprint planning, Team A commits to a critical API that Teams B and C need by sprint day 7 to meet their commitments. On day 5, Team A discovers the API requires a third-party security review that takes 10 business days. Team A's scrum master suggests they'll finish other stories and carry the API to next sprint. Teams B and C will miss their sprint goals without this dependency. How should you handle this situation?

← All questions

Study this topic