PMP Practice Question: People — Hybrid, Medium
Your hybrid project combines iterative software development with a traditional waterfall approach for regulatory compliance activities. The compliance manager, who has 20 years of experience, insists on reviewing every feature before it goes to the development team, creating a bottleneck. The development team complains this contradicts agile principles and slows their velocity by 40%. The compliance manager argues that skipping reviews could result in costly rework. How should you address this conflict?
Study this topic
- 📖Conflict Resolution: The 5 Techniques PMI Prefers on the PMP Exam
Understand the five conflict resolution techniques PMI emphasizes and learn which approaches the PMP exam favors in various project scenarios.
- 📖Mastering Conflict Resolution Scenarios for PMP Success
Learn proven conflict resolution techniques and navigate realistic PMP exam scenarios. Master the Thomas-Kilmann model and modern collaborative approaches.
- 🗂️Flashcards: Leadership, Team & Stakeholder Models
15 cards · quick recall practice
More People Questions
View all →You are managing a construction project using a predictive approach. The project is in the execution phase, and you have a baseline schedule with clearly defined milestones. One of your key team members, who is responsible for electrical installations, requests three weeks of leave for personal reasons during a critical phase of the project. This team member has specialized expertise that is difficult to replace. The leave would occur just before a major milestone delivery. What is the BEST course of action?
You are leading a manufacturing facility construction project following a predictive lifecycle. The project team consists of 15 members, including contractors and internal staff. After three months of work, you receive feedback from several team members that the weekly status meetings are too long and not productive. Team members feel they spend too much time listening to updates irrelevant to their work. The meetings currently last 90 minutes and cover all work packages. What is the best approach to address this concern?
You are leading a manufacturing implementation project using a predictive lifecycle. The project team consists of members from three different departments who have not worked together before. After one month of execution, you observe that team members primarily communicate within their departmental groups, and cross-functional collaboration is minimal. Work hand-offs between departments are experiencing delays and quality issues. The project charter emphasizes the importance of integrated teamwork for project success. What should you do to improve this situation?