Your organization is transitioning a large, multi-year infrastructure program to agile delivery. The program consists of five interdependent product teams, each running two-week sprints. After three program increments, dependencies between teams are causing frequent delays—Team A cannot complete their sprint commitments because they're waiting for API specifications from Team B, while Team C's database changes block Team D's integration testing. The program board shows 47 active dependencies across teams. Teams are becoming frustrated with blocked work and declining morale. What approach would best address these systemic dependency issues?