PMP Practice Question: Process — Hybrid, Hard

Your organization is implementing a new ERP system using a hybrid approach: data migration and infrastructure use waterfall phases, while business process configuration uses iterative cycles. After the second iteration, stakeholders from finance request significant changes to the chart of accounts structure, which impacts both the completed data migration design and upcoming infrastructure specifications. The change would add substantial business value but requires rework across both predictive and adaptive streams. The project is at 40% completion with moderate schedule pressure. How should you proceed?