ProcessPredictiveEasyECO: Process Task 1.1 - Manage conflicts

PMP Practice Question: Process — Predictive, Easy

You have just been assigned as the project manager for a bridge construction project that will take 18 months. The project charter has been signed by the sponsor, and you are beginning the planning phase. You need to identify all individuals, groups, and organizations that could impact or be impacted by the project. What process are you performing?