You are facilitating a project using a hybrid approach where requirements are gathered upfront but development occurs in two-week iterations. After four iterations, the team's velocity has been inconsistent: 28, 15, 32, and 18 story points respectively. The team reports that some iterations include significant work on technical infrastructure that doesn't directly relate to user stories but is necessary for the architecture. The project sponsor is concerned about the unpredictable pace and asks why the team cannot maintain consistent velocity. How should you address this situation?