PMP Practice Question: ProcessAgile, Medium

You are leading an agile project to develop a mobile application for a retail client. During sprint planning, the product owner presents 15 user stories, but the development team estimates they can only complete 8 stories based on their historical velocity of 32 story points per sprint. The product owner insists all 15 stories are critical for the upcoming product demo in three weeks. The total estimate for all 15 stories is 60 story points. What should you do first?