ProcessHybridHardECO: Process Task 2.7

You are leading a hybrid infrastructure modernization project with a $5M budget and 18-month timeline. The cloud migration work is being executed in two-week sprints using Scrum, while the network infrastructure upgrades follow a predictive schedule due to regulatory requirements and vendor dependencies. You've established a burn-up chart for the adaptive work and an earned value management system for the predictive work. At the 9-month mark, the cloud migration is progressing well with 60% of planned story points completed, but the network infrastructure shows a CPI of 0.78 and SPI of 0.85. The infrastructure delays are now blocking three upcoming cloud migration sprints. The sponsor asks for a realistic forecast of the final cost and completion date. What should you do?