PMP Practice Question: Process — Agile, Hard
An agile team developing a healthcare platform has maintained consistent velocity at 38 story points for six consecutive sprints. During the retrospective, technical debt items are repeatedly raised but never addressed because the product owner prioritizes new features to maintain competitive advantage. The lead architect warns that accumulated technical debt is increasing the time required for new features by approximately 30%, and estimates two full sprints would be needed to address critical technical debt. Code quality metrics show increasing defect rates and decreasing test coverage. What is the most appropriate action?
Study this topic
- 📖Quality Management in PMBOK 8: The Complete Performance Domain
Master the Quality performance domain in PMBOK 8 with focus on value delivery, customer satisfaction, and continuous improvement for the PMP exam.
- 📖PMP vs Six Sigma: Which Certification Path Is Right for You?
Compare PMP, Six Sigma Green Belt, and Black Belt certifications to understand their differences, career impacts, and which credential aligns best with your professional goals.
- 🗂️Flashcards: Agile, Scrum & Hybrid Concepts
15 cards · quick recall practice
More Process Questions
View all →You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. During month 6, you conduct an earned value analysis and discover that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks you to forecast the final project cost and determine what actions are needed. Using the current performance trends, what is the most appropriate estimate at completion (EAC) if you believe current variances are atypical and future work will be performed at the planned rate?
You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?
You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?