Your agile team has completed three sprints of a mobile application development project. During the retrospective, team members report that they consistently struggle to complete stories because dependencies on a third-party API team cause delays. The API team works in a different department and follows a waterfall approach with monthly release cycles. Several stories have been carried over to subsequent sprints, affecting the team's velocity. What should the product owner do to address this impediment?