PMP Practice Question: PeopleAgile, Medium

Your agile team has consistently delivered increments on time for the past four sprints. However, you notice during daily standups that one team member, Sarah, rarely speaks and only provides minimal updates. When she does contribute, her ideas are often valuable but she seems hesitant. Other team members are more vocal and sometimes talk over quieter members. The team velocity is good, but you're concerned about full team engagement. What is the most effective approach to ensure all voices are heard?

← All questions
📖

Study this topic

Breaking Into Project Management: PMP Certification for Career Changers

Career changers face unique challenges pursuing PMP certification. Learn how to meet eligibility requirements, build pro

More People Questions

View all →
1
MediumAgile

During sprint planning, your development team commits to 45 story points based on historical velocity. However, your product owner insists they must complete 60 story points this sprint because of a commitment made to a key stakeholder. The product owner argues that the team 'just needs to work harder' and threatens to escalate to senior management if the team doesn't comply. The team looks to you, the Scrum Master, for guidance. How should you respond?

2
MediumAgile

Your agile team has a new member, Sarah, who joined two weeks ago. Sarah has strong technical skills but comes from a traditional waterfall background. During the current sprint, you notice Sarah working in isolation, not updating the task board, and not asking for help despite her story being blocked. In the standup, she reports 'everything is fine' even though you can see she's struggling. Other team members have offered help, but she politely declines. What is the most effective way to help Sarah adapt to the agile team environment?

3
MediumAgile

Your agile team has been consistently meeting sprint commitments, but during a recent retrospective, team members admitted they have been padding estimates significantly to ensure they never miss a commitment. The team's capacity allows them to complete stories early, but they wait until late in the sprint to pull in additional work to avoid looking like they overcommitted. The product owner is frustrated because the team could be delivering more value. What should you do to address this behavior?