You are leading a pharmaceutical product development project following a waterfall approach. During the detailed design phase, your quality assurance lead raises concerns that the technical lead is making design decisions without consulting the regulatory compliance specialist, potentially creating future audit risks. When you investigate, you discover the technical lead believes the compliance specialist is being overly cautious and slowing down progress. The technical lead has 20 years of experience and has successfully delivered similar projects. The compliance specialist is newer to the company but has deep regulatory expertise. Your project has strict regulatory submission deadlines with significant financial penalties for delays. How should you address this situation?