PMP Practice Question: People — Predictive, Hard
You are managing a predictive construction project to build a new hospital wing with a 36-month timeline and $45M budget. Your team of 40 members includes architects, engineers, contractors, and hospital operational staff. At the 18-month mark, during earned value analysis, you identify that CPI is 0.92 and SPI is 0.88. In reviewing team performance data, you notice that the top 20% of your team members are producing 60% of the project value, while several team members are consistently underperforming against their assigned tasks. The human resource management plan includes a performance measurement approach, but you have not conducted formal performance reviews due to project pressures. Several stakeholders have commented on specific individuals not meeting expectations. Union agreements require 90-day notice for any personnel changes. What should you prioritize?
Study this topic
- 📖Earned Value Management: Your PMP Exam Formula Survival Guide
Master EVM formulas, interpret performance metrics, and tackle calculation questions with confidence. Essential Process domain knowledge for PMP success.
- 📖Cost Estimation Techniques: From ROM to Definitive Estimates
Master the cost estimation methods tested on the PMP exam, from rough order of magnitude to definitive estimates, with practical examples and calculation techniques.
- 🗂️Flashcards: Earned Value Management (EVM) Formulas
16 cards · quick recall practice
More People Questions
View all →You are managing a construction project using a predictive approach. The project is in the execution phase, and you have a baseline schedule with clearly defined milestones. One of your key team members, who is responsible for electrical installations, requests three weeks of leave for personal reasons during a critical phase of the project. This team member has specialized expertise that is difficult to replace. The leave would occur just before a major milestone delivery. What is the BEST course of action?
You are leading a manufacturing facility construction project following a predictive lifecycle. The project team consists of 15 members, including contractors and internal staff. After three months of work, you receive feedback from several team members that the weekly status meetings are too long and not productive. Team members feel they spend too much time listening to updates irrelevant to their work. The meetings currently last 90 minutes and cover all work packages. What is the best approach to address this concern?
You are leading a manufacturing implementation project using a predictive lifecycle. The project team consists of members from three different departments who have not worked together before. After one month of execution, you observe that team members primarily communicate within their departmental groups, and cross-functional collaboration is minimal. Work hand-offs between departments are experiencing delays and quality issues. The project charter emphasizes the importance of integrated teamwork for project success. What should you do to improve this situation?