ProcessHybridHardECO: Process Task 2.7

Your organization is executing a hybrid project to modernize its supply chain platform. The backend API development follows Scrum methodology, while hardware procurement and installation follow a predictive approach with fixed milestones tied to vendor contracts. You've established a cadence where API sprints are two weeks, and you conduct integrated planning every six weeks. During the third integrated planning session, the product owner requests prioritizing new API features that require hardware capabilities not included in the current procurement contract. The hardware lead indicates that modifying the contract will take 8-10 weeks and increase costs by 15%. The product owner argues these features are critical for competitive advantage. How should you proceed?