PMP Practice Question: Process — Hybrid, Medium

A project manager is overseeing a hybrid project to build a new e-commerce platform. The database architecture and payment integration are being developed using a predictive approach due to security requirements and third-party dependencies, while the website features are being delivered through Scrum sprints. The project has a fixed budget of $800,000 and a target completion date in nine months. After four months, earned value analysis shows the predictive components are over budget by 15% with an SPI of 0.85, while the Scrum team is delivering consistently within their sprint budgets. What should the project manager do?