PMP Guide — Empowering Project Managers
ProcessPredictiveHardECO: Process Task 2.1

PMP Practice Question: Process — Predictive, Hard

You are managing a large-scale infrastructure project with a 24-month timeline and a budget of $45 million. During the eighth month, earned value analysis shows: PV = $15M, EV = $12M, AC = $13.5M. Your sponsor is concerned about the schedule variance and asks whether the project can still finish on time within the original budget. You calculate TCPI based on BAC and determine it is 1.18. The project team's historical performance shows they typically achieve a CPI between 0.85 and 0.95 on similar projects. What is the MOST appropriate recommendation?

← All questions

Study this topic