PMP Practice Question: ProcessPredictive, Hard

You are managing a large infrastructure project with a 24-month timeline and a $15M budget. During month 14, your Cost Performance Index (CPI) is 0.89 and Schedule Performance Index (SPI) is 0.92. The project has consumed $9.2M of the budget. Your sponsor is concerned about cost overruns and demands that you reduce spending immediately. The critical path activities for the next three months include foundation work that requires specialized equipment already procured and scheduled. What should be your PRIMARY response to the sponsor's demand?