An insurance company is executing a hybrid project to modernize their claims processing system. Infrastructure and security hardening follow a predictive approach with stage gates, while claims processing features are delivered in two-week sprints with regular customer demos. During a retrospective, the development team expresses frustration that they frequently wait for infrastructure approvals that delay their ability to deploy completed features. The infrastructure team explains their governance process requires formal change advisory board reviews that occur monthly. What is the best approach to address this impediment?