ProcessHybridHardECO: Process Task 4.4

PMP Practice Question: Process — Hybrid, Hard

You are managing a government infrastructure project using a hybrid approach. The construction follows a predictive critical path method, while the smart building automation system uses incremental delivery with four-week iterations. You are currently in the execution phase. The construction team has encountered unexpected soil conditions requiring foundation redesign, delaying their schedule by three months. The automation system team has completed two iterations successfully and is ready to begin the third iteration, which requires installing sensors in the foundation area. The finance department is questioning why you are continuing to spend money on the automation system when the construction delay means those components cannot be installed on schedule. What is the MOST appropriate response?