Your Scrum team has completed their third sprint, and the Product Owner notices that the team's velocity has been inconsistent: 21 story points in Sprint 1, 15 in Sprint 2, and 18 in Sprint 3. The Product Owner is concerned about meeting the release deadline and asks you, as the Scrum Master, to commit to a specific velocity for the remaining sprints so stakeholders can plan accordingly. The team is still learning to work together and refining their estimation practices. What should you do?