PMP Practice Question: People — Predictive, Medium
You are leading a construction project using a predictive approach. The project management plan includes a resource management plan with clearly defined roles and responsibilities. A key team member, who is responsible for quality inspections on the critical path, has requested a two-week leave during a crucial phase of the project. This absence was not anticipated in the resource plan. The team member has unique expertise that is difficult to replace. What is the best course of action?
Study this topic
- 📖Coaching and Mentoring in Agile Teams: A PMP Perspective
Learn how servant leadership, coaching, and mentoring drive agile team performance. Essential knowledge for PMP candidates preparing for the 2026 exam's expanded agile focus.
- 📖Servant Leadership PMP Exam Scenarios Explained
Master servant leadership concepts for the PMP exam with practical scenarios, real-world examples, and detailed explanations aligned with PMBOK 8th Edition principles.
- 🗂️Flashcards: Leadership, Team & Stakeholder Models
15 cards · quick recall practice
More People Questions
View all →You are managing a construction project using a predictive approach. The project is in the execution phase, and you have a baseline schedule with clearly defined milestones. One of your key team members, who is responsible for electrical installations, requests three weeks of leave for personal reasons during a critical phase of the project. This team member has specialized expertise that is difficult to replace. The leave would occur just before a major milestone delivery. What is the BEST course of action?
You are leading a manufacturing facility construction project following a predictive lifecycle. The project team consists of 15 members, including contractors and internal staff. After three months of work, you receive feedback from several team members that the weekly status meetings are too long and not productive. Team members feel they spend too much time listening to updates irrelevant to their work. The meetings currently last 90 minutes and cover all work packages. What is the best approach to address this concern?
You are leading a manufacturing implementation project using a predictive lifecycle. The project team consists of members from three different departments who have not worked together before. After one month of execution, you observe that team members primarily communicate within their departmental groups, and cross-functional collaboration is minimal. Work hand-offs between departments are experiencing delays and quality issues. The project charter emphasizes the importance of integrated teamwork for project success. What should you do to improve this situation?