You are managing a hybrid project where the infrastructure team works in predictive mode with fixed milestones, while the application development team uses two-week Scrum sprints. During sprint planning, the development team commits to features that depend on network infrastructure scheduled for delivery in six weeks. Three sprints later, the infrastructure team reports a two-week delay due to vendor issues. The development team has partially completed dependent features and is requesting guidance on how to proceed. What should you do first?