PMP Practice Question: People — Predictive, Medium
Your predictive construction project has a baseline schedule of 18 months with defined milestones. You have a team of 40 people including contractors and full-time employees. The project sponsor has just informed you that due to budget constraints, three of your planned team members will not be available for the next phase starting in two months. These positions were critical to the resource management plan. The sponsor asks you to proceed with the reduced team and maintain the original schedule. What should you do first?
Study this topic
- 📖How to Document Project Hours for Your PMP Application
Master the art of documenting your project experience for the PMP application. Learn what PMI accepts, how to calculate hours accurately, and see real-world sample entries.
- 📖Scope Management: Defining and Controlling What Your Project Delivers
Master scope management techniques that prevent scope creep, ensure stakeholder alignment, and deliver exactly what your project commits to achieve.
- 🗂️Flashcards: Leadership, Team & Stakeholder Models
15 cards · quick recall practice
More People Questions
View all →You are managing a construction project using a predictive approach. The project is in the execution phase, and you have a baseline schedule with clearly defined milestones. One of your key team members, who is responsible for electrical installations, requests three weeks of leave for personal reasons during a critical phase of the project. This team member has specialized expertise that is difficult to replace. The leave would occur just before a major milestone delivery. What is the BEST course of action?
You are leading a manufacturing facility construction project following a predictive lifecycle. The project team consists of 15 members, including contractors and internal staff. After three months of work, you receive feedback from several team members that the weekly status meetings are too long and not productive. Team members feel they spend too much time listening to updates irrelevant to their work. The meetings currently last 90 minutes and cover all work packages. What is the best approach to address this concern?
You are leading a manufacturing implementation project using a predictive lifecycle. The project team consists of members from three different departments who have not worked together before. After one month of execution, you observe that team members primarily communicate within their departmental groups, and cross-functional collaboration is minimal. Work hand-offs between departments are experiencing delays and quality issues. The project charter emphasizes the importance of integrated teamwork for project success. What should you do to improve this situation?