ProcessHybridMediumECO: Process Task 3.1

PMP Practice Question: Process — Hybrid, Medium

You are managing a hybrid project for a financial services company where the infrastructure team uses predictive methods while the application development team uses Scrum. The infrastructure team has completed their work package on schedule, but the development team needs an additional sprint to integrate a regulatory compliance feature that was just clarified by the legal department. The infrastructure lead is concerned about team members being reassigned if they remain idle. What should you do first?