PMP Practice Question: Process — Predictive, Medium

Your construction project is 60% complete when you conduct an earned value analysis. The results show: PV = $500,000, EV = $450,000, AC = $480,000. The project sponsor asks you to provide a forecast of the final project cost. Based on current performance trends, you believe the cost variance is atypical and future work will be performed at the planned rate. What estimate at completion (EAC) should you report?