PMP Practice Question: People — Hybrid, Hard

Your hybrid project includes an offshore agile development team and an onshore predictive implementation team. The agile team's Scrum Master has been highly effective, and team members openly share impediments and collaborate well. However, you've noticed in the predictive workstream that team members rarely speak up in status meetings, several risks weren't reported until they became issues, and there's high reliance on formal change control processes even for minor decisions. The predictive team lead is experienced but tends to make decisions unilaterally. Cultural assessments show the offshore team comes from a high power-distance culture while the predictive team reflects the corporate risk-averse culture. What should you do to create greater psychological safety across both workstreams?

← All questions

Study this topic

More People Questions

View all →
1
MediumPredictive

You are managing a construction project using a predictive approach. The project is in the execution phase, and you have a baseline schedule with clearly defined milestones. One of your key team members, who is responsible for electrical installations, requests three weeks of leave for personal reasons during a critical phase of the project. This team member has specialized expertise that is difficult to replace. The leave would occur just before a major milestone delivery. What is the BEST course of action?

→
2
MediumPredictive

You are leading a manufacturing facility construction project following a predictive lifecycle. The project team consists of 15 members, including contractors and internal staff. After three months of work, you receive feedback from several team members that the weekly status meetings are too long and not productive. Team members feel they spend too much time listening to updates irrelevant to their work. The meetings currently last 90 minutes and cover all work packages. What is the best approach to address this concern?

→
3
MediumPredictive

You are leading a manufacturing implementation project using a predictive lifecycle. The project team consists of members from three different departments who have not worked together before. After one month of execution, you observe that team members primarily communicate within their departmental groups, and cross-functional collaboration is minimal. Work hand-offs between departments are experiencing delays and quality issues. The project charter emphasizes the importance of integrated teamwork for project success. What should you do to improve this situation?

→
PMP Practice Question — People · Hard | PMP Guide