Practice Questions
PMP Practice Questions
Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.
15 questions found
A global technology company is executing a predictive project to standardize enterprise resource planning (ERP) systems across 47 subsidiaries in 23 countries, with a 42-month timeline and $310M budget. During month 28, while implementing in the European region, the company's board approves a significant corporate restructuring that will consolidate the 47 subsidiaries into 12 global business units organized by product line rather than geography. This restructuring will change reporting structures, business processes, financial consolidation requirements, and potentially the entire ERP architecture. The project has successfully implemented the system in 18 subsidiaries, with 12 more in various implementation stages. The CIO asks the project manager to assess the impact and recommend how to proceed. What should the project manager do first?
August 16, 2026
A manufacturing company is executing a predictive project to build a $220M production facility for automotive components in an emerging market. The project is month 21 of a 36-month timeline, with building construction complete and equipment installation beginning. Economic conditions in the target market have deteriorated significantly—currency devaluation of 35%, increased import tariffs on raw materials, and two major automotive customers have delayed their regional expansion plans by 2-3 years. The original business case projected ROI of 18% over 8 years based on specific production volumes and pricing. The CFO has requested an updated financial analysis and is considering project termination or conversion to a smaller-scale facility. Equipment purchases worth $78M are committed but not yet delivered. What should the project manager do?
August 16, 2026
A financial services company is executing a core banking system replacement project using a predictive methodology with a 30-month timeline and $95M budget. The project has completed detailed requirements, design, and procurement phases. During the development phase (month 16), the company acquires a smaller competitor that uses a different technology platform. The merger integration team proposes consolidating onto a single platform, which would either require abandoning the current project (wasting $42M invested) or forcing the acquired bank to migrate twice—first to their interim platform, then to the new system within 18 months. The PMO director asks the project manager to evaluate strategic options. Regulatory requirements mandate system consolidation within 24 months of acquisition closing. What analysis should the project manager prioritize?
August 16, 2026
A government infrastructure project worth $420M is in its execution phase using a predictive approach with a 5-year timeline. The project is building a regional transportation hub with multiple contractors. Three years into execution, a new administration takes office with different policy priorities and appoints a new agency director who questions the project's strategic alignment. The director requests a comprehensive benefits realization review before authorizing the next $150M funding tranche. Current earned value metrics show: SPI = 0.92, CPI = 0.88, with 58% of work completed. The project business case was approved under different economic assumptions, and inflation has increased costs by 14%. How should the project manager approach this situation?
August 16, 2026
A multinational pharmaceutical company is executing a predictive drug development project with a 4-year timeline and $180M budget. During year 2, a competitor receives FDA fast-track designation for a similar drug, potentially reducing the market window by 18 months. The project sponsor pressures the project manager to compress the schedule by overlapping clinical trial phases, which would violate regulatory protocols and risk patient safety. The governance board is split—some members prioritize speed-to-market while others emphasize compliance. Financial analysts project a $250M revenue loss if the competitor launches first. What should the project manager do first?
August 16, 2026
You are managing a predictive infrastructure project for a public utility company with a detailed WBS, approved baseline, and 24-month timeline. At month 16, a new CEO joins the organization and introduces a strategic initiative to adopt renewable energy sources. She directs that your project must now incorporate solar panel installations and battery storage systems, representing a 40% scope increase. The CEO expects the same completion date, stating 'we need to show renewable commitment to our board and regulators.' Your project sponsor privately tells you to 'make it work' to avoid conflict with the new executive. The additional scope has not gone through formal change control, and preliminary analysis suggests the original budget is insufficient. What is your best course of action?
July 29, 2026
Your organization has been awarded a predictive project to implement a financial system for a client in a country with strict data sovereignty laws. The project plan, developed six months ago, specified using your company's standard cloud infrastructure hosted in your home country. Two months into the eight-month project, the client's government issues new guidance clarifying that all financial data must be processed and stored within national borders with no exceptions. Your cloud provider has no data centers in the client's country and establishing one would take 14 months. The client will not grant an extension beyond 60 days. Senior management is considering proceeding with the original plan and addressing compliance 'later.' What should you do?
July 29, 2026
You are managing a predictive pharmaceutical research project that requires approval from multiple regulatory bodies across different countries. The project is structured with sequential phase gates, and investment in each subsequent phase depends on passing regulatory reviews. During Phase 2 clinical trials, preliminary data suggests the drug is effective but the European Medicines Agency (EMA) requests additional long-term safety data that was not originally planned, while the FDA is satisfied with current protocols. This additional study will cost $3.2 million and delay market entry by 18 months. Your CFO argues the company should focus only on FDA approval and enter the European market later. What should you recommend?
July 29, 2026
Your organization is executing a three-year government defense project using a predictive approach with strict earned value management (EVM) reporting requirements. At the 15-month progress review, the Cost Performance Index (CPI) is 0.78 and the Schedule Performance Index (SPI) is 0.82. The customer is threatening contract termination due to poor performance. Your executive sponsor suggests re-baselining the project to show improved metrics for the next reporting period. The original baseline was approved by all stakeholders including the government oversight committee. What is the most appropriate action?
July 29, 2026
You are managing a predictive construction project with a fixed-price contract worth $8 million. Six months into the 18-month project, a new environmental regulation is enacted that requires additional soil remediation work not included in the original scope. The customer insists this should be absorbed within the existing contract price, citing the fixed-price nature of the agreement. Your legal team confirms the regulation was not foreseeable at contract signing. The additional work is estimated at $450,000 and will add two months to the schedule. What should be your primary course of action?
July 29, 2026
A project manager is leading a predictive ERP implementation project for a retail organization. The project is structured with a detailed WBS, approved baseline, and stage-gate governance. During the design phase, the organization acquires a competitor with 40 retail locations, increasing the company size by 35%. The integration team requests that the ERP project expand scope to include the acquired locations, which would require additional modules, data migration from legacy systems, and extended training. The business case ROI was calculated based on the original organization size. Executive leadership wants to know whether to expand this project's scope or manage the acquisition locations through a separate integration project. What is the most important factor the project manager should analyze in formulating a recommendation?
June 22, 2026
A government contractor is managing a predictive defense project with strict compliance requirements and a fixed-price contract. Midway through execution, new export control regulations are implemented that reclassify certain technical data the project team has been sharing with an offshore subcontractor. Immediate compliance requires terminating the subcontractor relationship and transitioning work to domestic resources, which will increase costs by 35% and extend the timeline by 3 months. The contract includes a changes clause for regulatory compliance, but invoking it requires demonstrating that compliance was unforeseeable at contract signing. Legal review suggests the regulatory change was predictable based on geopolitical trends. What should the project manager do?
June 22, 2026
A pharmaceutical company is executing a predictive project to build a new quality control laboratory, scheduled for completion in 14 months. Six months into execution, a competitor announces a breakthrough product that significantly changes market dynamics. The executive team convenes an emergency strategy session and decides to pivot the company's product portfolio, which will require different laboratory specifications and testing capabilities than originally planned. The current project is 40% complete with $3.2M spent of the $7M budget. Preliminary analysis suggests retrofitting the in-progress facility would cost $2.1M additional, while stopping and redesigning would cost $1.8M but delay completion by 5 months. What should the project manager recommend?
June 22, 2026
A project manager is leading a multi-year infrastructure project using a predictive approach. The organization's CFO announces a strategic shift toward improving EBITDA margins, requiring all departments to reduce operating expenses by 12% over the next fiscal year. The project is currently on track with its approved budget, but this initiative could impact resource allocation and vendor contracts already negotiated. Several project team members express concern that cost-cutting measures will compromise quality deliverables. The project's ROI calculation was based on completing all scope within the original quality parameters. How should the project manager address this organizational change?
June 22, 2026
A manufacturing company is executing a predictive project to build a new production facility. During the execution phase, new environmental regulations are enacted that require additional wastewater treatment infrastructure not originally planned. The project manager reviews the cost baseline and schedule baseline, noting that incorporating these requirements will exceed the approved budget by 18% and delay completion by 4 months. The project sponsor indicates that these regulations must be complied with, but the business case assumed facility operations would begin in 6 months to meet seasonal demand. What should the project manager do first?
June 22, 2026
